The existing parking lot at Buda City Park will be replaced with all-weather surface parking spaces.

Contracted Firm: Doucet & Associates

Current Status:

  • Doucet & Associates finalized construction plans in late-October and the project was released for bidding in early December 2023.

  • City Council’s evaluation and selection of a contractor occurred on Jan. 3, 2024. City Council awarded the construction contract to most qualified low bidder, Harris Road Company of Wimberley, Texas, for $603,943.83. Two parking lots were awarded. The North Parking Lot included 70 parking spaces, and the West Parking Lot included 51 spaces, totaling 121 new parking spaces in City Park.

  • The contractor began construction of the parking lots in late-January 2024. The parking lots are constructed and the project is in the final close out process.

  • View the plan here.

    See previous updates ››

Bond Amount: $607,500